EE/CpE 415/423 – 416/424
2001 Fall – 2002 Spring
WEEKLY STATUS REPORT
Group No. :__5___ Date: __ 4/22/02_________ Report No.:__ ___13_____
Project Title: Volleyball Project – Image Tagging and Filing System
Group Leader: ____Anthony Sanzari__ Advisor:
__Hong Man___
Sponsor/Client: ________Stevens
Number of Hours Spent on Project by Group in Past Week:
____34______
Project on Schedule: YES __________ NO _____X__________
Weekly Status:
This week our team has continued the implementation phase of our ITS-Image Tracking System, software application and is finishing up some of the final details of the application to get it ready for display day. We are still working out the last few issues with the ITS main application at this point, performing mostly debugging problems and trying to make the user-interface for “friendly.” We have completed the incorporation of the media player into our ITS interface, and have also completed the integration of the MS Access database which is used to collect all recorded statistical and playback information.
The majority of our time
from now, until the end of the semester, will be on refining and debugging the
application, and redesigning the key-stroke capture module which was not
compatible with our final ITS application.
This module is currently being “re-worked” and by weeks end we hope to
have it ready for integration and debugging into the core module. Depending on our relative success with this
key-logging module will determine the amount of time we have to groom the final
application.