 |
Project Status
|
|
 |
May 2002
The final month of the project was great.
We wrote up our Senior Design Final Report. It had over 50 pages of
content, which addresses the various stages of the project, provides complete
test results with graphs, and much more.
We also had the chance to do different demonstrations for different
professors, who all were very impressed with it.
Later this month we will be turing in our keys. This marks the end of
our involvement in the Project. However, a group of upperclassmen students
will be implementing similar boards based on our design as a Technogenesis
summer project.
|
|
|
 |
April 2002
In this month we finished the most significant phases of the project.
We were able to finally implement our design, and connect the components
to each other. We also did the back panel power wiring.
The system done, we were able to perform overall system testing, both
with wires and wirelessly. Our system worked as good as we expected. For
wireless test runs and demonstration, we had the signal generator broadcasting
Sin waves at frequencies around 2.4 GHz, and our system was capturing the
signals wirelessly, and after its two phase down conversion, was outputting
the resulting signal on the computer screen.
In addition to the system, we were able to create a LabView software
utility that plots the output signal of our system in real-time, allows
storing the output as a CSV or TXT file, or e-mail it for further analysis.
April 24th was the Senior Design day! We moved our system to the Howe
center and we performed demos and explained our project to the guests.
We had the project oral presentation in B-118 on April 30th, in which
we discussed the project and the various technical and financial aspects
of it. It went very well. |
|
|
 |
4th Week of March 2002
The local oscillator was powered and it worked beautifully. Testing
of the LO was carried out, and it worked just as expected. Now that we
have the LO working, we also took the chance to test the demodulator at
various frequencies of interest.
On another side of the project, work is being done to make computers
"talk" to our signal generator. This will be used for our senior design
day demonstration, as we will have the signal generator generate various
frequencies, and then wirelessly transmit it to our RF receiver, which
will pick the signals up. we will demonstrate that by showing the output
of the RF on another PC. |
|
|
 |
3rd Week of March 2002
We were able to create our own SMA cables for power (soldered regular
wires to SMA male connectors). That being done, we are now ready to test
the switch.
Testing of the switch was done successfully, both ends were tested for
leakage. |
|
|
 |
2nd Week of March 2002
Call us nerds, but we spent the spring break in the lab. This week was
very important and significant to our progress, as we were able to get
started with testing (Finally!). We were able to test the two filters used.
We soldered the two amplifiers to wires, and were able to test them (the
amplifiers) as well. Testing results for the filters, amplifiers, and the
rest of the components are available in the "Documents" section of this
web site.
The Local Oscillator is a generic one, so we had to "program it" to
work with our project. After working the equations and finding the pins
assignment, we customized a db-25 ribbon cable so that the LO will function
safely and provide us with 70 MHz.
The GAGE data acquisition cards were installed in the system and they
are working fine now.
In addition, we drilled holes for the receiver side, and took care of
many miscellaneous issues in the system. |
|
|
 |
1st Week of March 2002
The PC came back and was fine now. We were able to finally get it to
work.
We put the components on the board to see how they will fit.
Final preparation for testing was done at this time as well. We are
very careful in testing as the components and testing devices are really
sensitive and can easily be damaged. |
|
|
 |
February 2002
We continued setting up the lab. The industrial PC we purchased gave
us a hard time when we tried to install the Data Acquisition cards from
Gage technology. It had some hardware problems and we had to return it
back to the manufacturer to replace defective pieces.
In this month we also were able to draw up the testing procedures and
phases. Testing is a fundamental part of this project. |
|
|
 |
January 2002
Setting up the lab. After we got a small private lab in B125, we started
moving devices and components in there and setting up the lab for the project. |
|
|
| November - December 2001
We finally settled on a design prototype to implement. Noise figure
calculations, research to find components was done at that time. This stage
was spent in careful planning for things to come, we wanted everything
to be ready so as to get started as soon as possible the next semester. |
 |
|
|
|
|